Glossary · Energy industry & energy transition
Interconnector
An interconnector is a transmission line that links the electricity grids of two states or bidding zones. In German it is also called a Kuppelleitung, and in EU law a Verbindungsleitung (interconnector). Regulation (EU) 2019/943 on the internal market for electricity describes it as a transmission line that crosses or spans a border between Member States and connects their national transmission systems. In everyday usage, links to third countries such as Norway or the United Kingdom are also called interconnectors. An interconnector connects two transmission grids and thus usually also two market areas. It does not generate electricity itself and does not reduce demand. However, it allows electrical energy and power to be exchanged in both directions.
Technical design
Interconnectors exist as three-phase AC lines (alternating current) or as high-voltage direct current (HVDC) transmission. AC links couple grids that lie within the same synchronous area. One example is the Continental European interconnected grid, whose grids run at the same frequency. There, power flow can be controlled only to a limited extent, because it distributes itself according to the electrical properties of the entire meshed grid. HVDC links using direct current work differently: converter stations at both ends convert the current. This allows the transmitted power to be set precisely. In addition, an HVDC link can also connect grids that do not run synchronously, such as Scandinavia or Great Britain with Continental Europe.
Long submarine cables are almost always built as HVDC. The main reason: because of its high capacitance, a three-phase AC cable has to continuously draw charging currents. Beyond a few dozen kilometres, these reactive currents consume a large share of the transmission capability. DC cables do not have this problem. On the other hand, converter stations cost a great deal of money and cause losses of their own. HVDC is therefore worthwhile above all over long distances, for submarine cables and for links between asynchronous grids.
Power, energy and tradable capacity
The size of an interconnector is stated by its transmission capacity in megawatts or gigawatts. This is an instantaneous quantity, not an amount of energy. A 1,000-megawatt line can transmit at most 1,000 megawatt-hours in one hour, and even that only if it is fully loaded the whole time. Over a year, that would theoretically be 8.76 terawatt-hours. In practice, considerably less is usually transmitted. Reasons include maintenance, outages, changing flow directions and hours with equal prices on both sides, in which trading is not worthwhile.
The physical rated capacity of a line is often confused with the capacity available for trading. Grid operators must run the grid in such a way that even the failure of an important piece of equipment does not trigger a chain reaction. This principle is called the (n-1) criterion. Further deductions result from reliability margins, loop flows and domestic grid congestion. So that domestic congestion is not shifted onto the borders at the expense of trading, Regulation (EU) 2019/943 sets a minimum value. At borders with coordinated net transmission capacity (NTC), at least 70 percent of the transmission capacity that can be used securely after deducting contingencies must be made available for cross-border trading. For flow-based capacity calculation, a corresponding margin applies on the critical network elements. According to the recitals, the remaining 30 percent covers, among other things, the reliability margin, loop flows and internal flows. Member States with structural congestion were able to approach this value gradually through action plans.
Market coupling and power flow
In the European electricity market, capacity between bidding zones is largely allocated implicitly through market coupling in day-ahead and intraday trading. The exchange results of all coupled zones are calculated jointly. Electricity flows economically from the cheaper to the more expensive price zone as long as capacity is free. If enough capacity is available, prices converge. If it is scarce, a price difference remains. In that case it is not the electricity itself that is scarce, but the transport between the zones.
Physically, electricity does not abide by trade contracts. In meshed three-phase AC grids, loop flows arise: a transaction between two countries can load lines in a third country. For this reason, grid operators calculate capacity in a coordinated way. They do not simply add up the rated values of the individual border lines. How much an interconnector can actually deliver therefore depends on the state of the entire grid. This includes domestic lines, transformers, voltage control and grid protection.
Distinction from import, export and security of supply
An interconnector is not the same as electricity imports. Import and export describe the direction of trade or of the balance. The interconnector is the infrastructure that makes this exchange possible. The same line can bring electricity into the country in the morning and out of it in the evening, depending on how wind, sun, load and power plant dispatch change.
Interconnectors strengthen security of supply, because several countries can help each other out. However, they do not simply replace a country's own firm capacity. If a large-scale Dunkelflaute (prolonged low wind and solar output) hits several countries at the same time, or if the neighbours themselves have a high residual load, the power they can supply falls. Then the line is free, but the electricity is missing on the other side. Conversely, enough generation may be available, but a transport bottleneck prevents it from being delivered. Statements such as “we can just import” therefore describe a possibility, not a guarantee. They only become reliable once the availability of the line, the weather situation in the neighbouring countries, their power plant availability and the rules for crisis situations are taken into account.
Significance for the European electricity system
Wind and solar power occur at different times in different regions. The load profiles of countries also differ. Via interconnectors, hydropower in Scandinavia and the Alps, nuclear power in France, wind power in the North Sea, solar power in Southern Europe and flexible power plants work together more closely than would be possible in isolated national systems. Surpluses have to be curtailed less often, and cheaper plants displace more expensive ones across borders. This lowers overall costs. Storage, controllable demand and domestic grid expansion nevertheless remain necessary. If a border is opened for trading even though internal congestion lies behind it, the costs arise elsewhere, for example for redispatch.
The EU has set itself the target that every Member State reach an electricity interconnection level of at least 15 percent by 2030. This is anchored in law in the Governance Regulation (EU) 2018/1999. Member States must state in their national energy and climate plans which interconnection level they are aiming for and how they intend to achieve it.
Misunderstandings about “electricity from abroad”
High imports are often interpreted as a sign of shortage. In a coupled market, however, a country often imports simply because electricity across the border is currently cheaper than its own generation, even if its own power plants would be available. Conversely, high exports are not automatically a sign of strength. They can also result from inflexible plants, low demand or surpluses of wind and solar power. An annual balance alone therefore says little. More meaningful are power flows, price differences, grid congestion, redispatch volumes and how imports and exports are distributed across the hours.
Congestion revenues, financing and regulation
-
Congestion revenues: If capacity is scarce, a price difference arises between two zones. Multiplied by the traded volume, this yields the congestion revenues, which are due to the operator of the link.
-
Use restriction: Under Article 19 of Regulation (EU) 2019/943, these revenues must be used primarily for two purposes: first, to ensure that the allocated capacity is actually available, including compensation if committed capacity is curtailed. Second, to maintain or expand cross-zonal capacities, for example through grid investments. Whatever remains afterwards may reduce network charges only under regulatory conditions. The Bundesnetzagentur (German Federal Network Agency) publishes a report on this every year.
-
Regulated and merchant lines: Most interconnectors are owned by transmission system operators and financed through regulated network charges. On application, new interconnectors can be partially exempted from the rules. This exemption is governed by Article 63 of Regulation (EU) 2019/943. Such so-called merchant interconnectors are then financed predominantly from congestion revenues.
-
Planning: Transmission system operators, ENTSO-E with the European network development plan, the national regulatory authorities, ACER and the rules for projects of common interest are involved in planning and assessment. The factors weighed are network benefit, security of supply, environmental impacts, permitting risks and the allocation of costs between the countries.
The term interconnector thus means more than a line at the border. It brings together physical electricity transport, European trading, grid security and political coordination. An interconnector widens the room for manoeuvre of an electricity system. It does not replace generation, storage and clear rules for congestion and crisis situations.
Sources
- Verordnung (EU) 2019/943 über den Elektrizitätsbinnenmarkt (Neufassung) — Europäisches Parlament und Rat / EUR-Lex; 2019-06-05. Art. 2 Nr. 1 (Begriff Verbindungsleitung); Art. 16 Abs. 8 (70-%-Mindestkapazität); Art. 19 (Engpasserlöse); Art. 63 (Ausnahmen für neue Verbindungsleitungen)
- Regulation (EU) 2019/943 on the internal market for electricity — EUR-Lex; 2019-06-05. Erwägungsgrund 28; Art. 16 Abs. 8 Buchst. a und b
- Erlöse aus grenzüberschreitendem Engpassmanagement im Zeitraum 01.01.2020 bis 31.12.2020 — Bundesnetzagentur; unbekannt (Berichtsjahr 2020). Einleitung, Bezug auf Art. 19 Abs. 2 und 5 VO (EU) 2019/943
- Verordnung (EU) 2018/1999 über das Governance-System für die Energieunion und für den Klimaschutz (konsolidierte Fassung) — EUR-Lex; 2023-05-16 (konsolidierte Fassung). Art. 4 Buchst. d Nr. 1
- Schlussanträge in der Rechtssache C-454/18 (Baltic Cable) — Gerichtshof der Europäischen Union / EUR-Lex; unbekannt. Randnummern zu Engpasserlösen
Related glossary entries
- transmission grids
- direct current
- price zone
- loop flows
- security of supply
- Dunkelflaute
- redispatch
- congestion revenues