Glossary · Energy industry & energy transition
Additionality criterion for green hydrogen
The additionality criterion for green hydrogen requires that the electricity used to produce hydrogen by electrolysis comes from newly built renewable installations. Existing renewable electricity is therefore not simply to be rebooked. The idea builds on the general concept of additionality: a new electricity consumer should at the same time ensure that additional wind or solar installations are built. In the EU, the criterion is not a loose industry term. It is laid down in law in Delegated Regulation (EU) 2023/1184. This regulation determines when electricity used to produce renewable fuels of non-biological origin (RFNBO) counts as fully renewable.
The technical starting point is simple. An electrolyser uses electricity to split water into hydrogen and oxygen. How climate-friendly the hydrogen is therefore depends almost entirely on the electricity used. If a large new load draws electricity from the grid, that demand has to be met somewhere. Without new renewable installations, depending on the hour and region, fossil power plants run longer, or less renewable electricity remains available for other consumers. The additionality criterion is meant to prevent this displacement. A mere accounting claim thus becomes an obligation to invest.
What the EU rule specifically requires
Under Article 5 of Regulation 2023/1184, an electricity generation installation counts as additional if two conditions are met. First, it may have entered into operation no more than 36 months before the installation producing the RFNBO. Second, it may not have received operating or investment aid. The regulation provides exceptions for narrowly defined cases. If an existing electrolyser at the same site is expanded within 36 months of its commissioning, the new capacity counts as if it had entered into operation at the same time as the original installation. The rules apply regardless of whether the fuel is produced in the EU or in a third country. They therefore also affect imports.
In practice, the regulation distinguishes two routes. With a direct connection, the electrolyser is connected directly to a wind or solar installation and draws no grid electricity. An age limit for the generation installation also applies in this case. With grid sourcing, the electricity is drawn via the public grid. The operator must then generally demonstrate one or more electricity supply contracts, that is, a Power Purchase Agreement (PPA) with installations that meet the additionality conditions. In addition, there are requirements for temporal and geographical correlation.
Temporal and geographical correlation
Additionality asks whether new generation capacity is created. Temporal correlation asks whether hydrogen production and renewable generation match in time. Under current law, matching within the same calendar month is sufficient until 31 December 2029. From 1 January 2030, matching must be done hourly, which corresponds to the principle of temporal matching. An example shows the difference: an electrolyser consumes 100 gigawatt hours a year, and a wind farm also generates 100 gigawatt hours. On paper, the allocation looks complete. But if the electrolyser also runs during windless night hours, in those hours it is in fact drawing electricity from the general generation mix. Geographical correlation requires in principle that the generation installation and the electrolyser are located in the same bidding zone. Under narrow conditions, interconnected bidding zones or offshore bidding zones are also permitted.
Transitional rules and exceptions
An important transitional rule applies to early projects. Article 11 suspends the two additionality conditions, namely the 36-month limit and the prohibition of aid, for electrolysers that enter into operation before 1 January 2028. The exception applies until 1 January 2038. Capacity added after 1 January 2028 is not covered. One distinction is important: the transitional rule concerns only additionality. The requirements for electricity supply contracts and for temporal and geographical correlation continue to apply. The obligation of hourly matching from 2030 is therefore not postponed.
In addition, Article 4 contains special cases for grid electricity. In bidding zones with a very high average share of renewable electricity, grid electricity can, under certain conditions, count as renewable without a separate proof of additionality. A simplified route is also provided in zones with very low emission intensity of electricity. Likewise, electricity can be counted that is consumed in periods in which it would otherwise be lost through curtailing redispatch. The exact thresholds and calculation rules are set out in the regulation itself. For a specific project, they should be checked against the consolidated version.
Distinction from guarantees of origin and green electricity tariffs
Additionality is often confused with the guarantee of origin. A guarantee of origin proves that a certain quantity of renewable electricity was generated somewhere. It says nothing about whether this installation was built because of the electrolyser, and nothing about temporal or geographical proximity. Guarantees of origin or a general green electricity tariff are therefore not sufficient for classification as an RFNBO. The terms should also be kept apart: renewable describes the energy source, low-emission the greenhouse gas balance within a defined system boundary. Additional, by contrast, describes whether new demand is linked to newly built generation. A wind farm that has been running for 15 years generates renewable electricity, but it is not additional for a new electrolyser.
A terminological point should also be noted: “green hydrogen” is a term from general usage, comparable to other hydrogen colours. Legally, what is decisive in the EU is classification as an RFNBO. Only this determines whether hydrogen and the e-fuels produced from it count towards the targets of the Renewable Energy Directive in transport and industry. Anyone who means green hydrogen within the meaning of EU law must therefore meet the RFNBO criteria.
Significance for the power system, grids and industry
Hydrogen can require very large quantities of electricity. When refineries, the chemical industry, steelmaking or shipping and aviation switch to hydrogen and power-to-X products, part of their energy demand shifts to the power sector. This makes sense for climate policy if the expansion of renewable generation grows alongside it. Without this expansion, pressure on generation, grids and system operation increases. An electrolyser is a controllable load and thus offers flexibility. If it runs in hours with plenty of wind and solar power and pauses in tight hours, it facilitates the integration of renewable energies. If, by contrast, it runs steadily because a downstream industrial process needs hydrogen constantly, it increases the load even in hours with high residual load. The need for hydrogen storage or for oversizing generation then rises.
For investors, the criterion means planning effort. Besides the grid connection and offtaker, they need a reliable electricity procurement from new installations that is closely tied to the commissioning date of the electrolyser. Even small delays can jeopardise the 36-month limit. The prohibition of aid also restricts the choice of installations, because many wind and solar projects receive state support. The site thus becomes a question for the whole system: proximity to renewable generation, grid capacity, water availability and industrial demand must fit together. The criterion is not a grid rule. But it steers where investment goes.
Criticism and ongoing review
The set of rules is contested. Supporters consider additionality and hourly matching necessary so that RFNBOs actually reduce emissions and do not indirectly trigger fossil electricity generation. Critics from industry, the energy sector and individual Member States regard the requirements as an obstacle to market ramp-up. In their view, they increase electricity procurement costs and reduce the utilisation of electrolysers. Originally, the Commission was to submit a report on the impacts by 1 July 2028. At the end of March 2026, senior officials from Germany, Spain, the Netherlands, Austria and Poland called for the review to be brought forward and completed in 2026. In its communication “AccelerateEU” of April 2026, the Commission then announced a targeted revision of the criteria. Industry associations are demanding, among other things, that the transitional period for additionality be extended to at least 2035 and that hourly matching be postponed.
As of the end of November 2026, the rules of Regulation 2023/1184 described above continue to apply unchanged, as far as can be traced in the sources reviewed. Anyone planning projects should check whether the Commission has in the meantime adopted an amending act and what grandfathering rules it may contain.
Typical misunderstandings
-
“Electrolysis is always green.” Electrolysis is only the conversion process. With electricity from a grid dominated by fossil generation, electrolysis hydrogen can even cause higher emissions than hydrogen produced conventionally from natural gas.
-
“A balanced annual account is enough.” Under EU law, from 2030 not even monthly matching is sufficient; then the hour counts.
-
“The transitional rule until 2038 exempts from all obligations.” It concerns only the age and aid-free status of the generation installation, not temporal and geographical correlation.
-
“Additionality only makes hydrogen more expensive.” The criterion causes effort for contracts, evidence and project coordination. Without additionality, however, the costs do not disappear. They then appear as higher emissions or as displacement in the power system.
The additionality criterion thus does not describe a property of the hydrogen molecule. It is a rule on how electricity, investment and climate balance are allocated to one another. Its strength lies in coupling hydrogen production to the expansion of renewable generation. On its own, however, it guarantees neither grid-serving behaviour nor low costs nor an adequate hydrogen supply. For that, suitable sites, flexible operation, storage and clear certification are additionally needed.
Sources
- Delegierte Verordnung (EU) 2023/1184 der Kommission vom 10. Februar 2023 (RFNBO-Methode) — Europäische Union, EUR-Lex; 2023-02-10. Art. 3, Art. 5 (Zusätzlichkeit), Art. 11 (Übergangszeitraum)
- Commission Delegated Regulation (EU) 2023/1184 (PDF, englische Fassung) — Europäische Union, EUR-Lex; 2023-02-10. Erwägungsgrund 18, Art. 4, Art. 10
- Renewable hydrogen in the EU: a framework under pressure — Stibbe; 2026 (ca. Mai, genaues Datum unbekannt). Abschnitte zur RFNBO-Definition und zum Brief der Generaldirektoren
- Joint Letter calling for Speedy Targeted Amendment Process of the Delegated Act (EU) 2023/1184 on RFNBO Production Criteria — Hydrogen Europe u. a. (gemeinsamer Verbändebrief); 2026-07-08. Seite 1, Forderungsliste
Related glossary entries
- additionality
- RFNBO
- electrolyser
- Power Purchase Agreement
- temporal matching
- redispatch
- guarantee of origin
- green hydrogen
- power-to-X
- flexibility
- residual load